Region: South West
The Edithmead (J22) to Exminster (J31) section of M5
INDEX TO SECTIONS M5 Bridgwater By-pass (J23 to J24) This contract, which included the Huntworth Viaduct, was awarded to Cementation Ltd. for a tender sum of £5.26m. The start date was June 1971 and it was opened in December 1973. The length was 4.9 miles and it included the Huntworth interchange. Southeast of Bridgwater the motorway crosses the River Parrot, the Bristol-Exeter Railway, the Taunton to Bridgwater Canal and two minor roads; furthermore as the alluvium at the site would only support a lightweight embankment, a viaduct carrying the motorway for about half a mile over these facilities was an economic proposition. The design was a twin steel box girder construction with a composite reinforced concrete deck. The main spans are 166 ft. and there are seventeen spans with columns founded on large diameter bored piles which extend well into the keuper marl beneath the alluvium. The design of the structure was undertaken before the publication of the report of the Merrison Committee on Box Girder Bridges. However during the preparation of the design the Engineers in the Sub-Unit worked closely with experts at the Imperial College of Science. Advice which emerged from the University enabled factors to be included in the design which minimized the ultimate problems at the reappraisal stage. In fact only a small amount of extra steel was required mainly in the webs of the box girder compression flanges. The embankments to the north of the viaduct were constructed in PFA and surcharged to accelerate settlement. In addition to the viaduct six other bridges were constructed as part of the contract. Settlement on the Alluvium In the previous paragraphs covering the M5 from Bristol to Bridgwater references have been made to the research at Avonmouth, to the use of lightweight filling materials and to surcharging of embankments to accelerate settlement of the alluvium across the Somerset Levels. On much of the work the Consulting Engineers and the Sub-Unit were advised on design and monitoring of settlement. On completion of the Motorway the Department of Transport agreed to an annual monitoring of the surface levels of the carriageways for a period of some ten years to determine how actual settlements corresponded with the predicted values. Regrettably the results of this work seem to have been lost. However it is understood from hearsay that the results, as might be expected with such a large variation in conditions of the alluvium, were very variable and included extremes from much lower to much larger settlements than predicted. Perhaps the most obvious evidence of continued settlement was at some overbridge sites where the pier foundations were on piles. In one case the evidence showed settlement of as much as a foot after ten years. The variability of settlement was also clearly exhibited longitudinally along the carriageway by the undulations which were particularly apparent in long wheelbase vehicles such as coaches. Conditions now, approaching thirty years on, have improved considerably after resurfacing and it is apparent the rate of settlement has reduced considerably. M5 Taunton By-Pass (J25 to J26) The Cementation-McGregor consortium were awarded the contract for this 6.9 mile length for a tender sum of £5.02m. The start date was March 1972 and the scheme was opened in April 1974. The scheme required the construction of 14 bridges, interchanges at Blackbrook and Chelston (east of Wellington) and two link roads joining the motorway interchanges to the A38. This was the first section of the M5 constructed with a concrete pavement. The contract was one of the first to be designed using a new Department specification which encouraged the construction of un-reinforced concrete pavements of reduced thickness on various sub-base depths. In fact the difference in tender price between concrete and a flexible asphalt construction was very small. At the time, and because of some concerns about the specification, the Chief Engineer of the Sub-Unit recommended that the flexible solution be adopted, but this was not accepted. McGregor's had much experience of operating a Guntert & Zimmerman slip-form concrete paver and had carried out trials for the Department in Nottinghamshire. Techniques had been developed for inserting dowel bars automatically into the contraction joints formed at 6 metre centres. Similarly tie bars were inserted across the two longitudinal joints and preformed joint seals were vibrated into the concrete. The specification required a protective "thatch" be retained on the earthworks until the formation was prepared and the sub-base was constructed. The profile of the road meant that the most of the soil at formation was keuper marl which at its optimum moisture has high Californian Bearing Ratios (CBR's). However if allowed to become saturated the bearing value falls to very low figures. The design requirements for the pavement, which it is believed were based on the concept that the formation would be maintained at the optimum moisture content, were for a 10.2 ins deep unreinforced concrete slab on a 3 ins of quality sub-base (type1). In order to haul supplies of sub-base materials and concrete to the paving machine, and avoid formation damage, the Contractor constructed a 9 inch sub-base on the north bound carriageway, materials were then fed across the central reservation to build the south bound carriageway. The added strength of this haul road meant that the concrete pavement thickness was reduced to 9.2 ins. The potential for future problems, due to sub-grade softening because of water ingress, concerned the designers in the Sub-Unit. Experience elsewhere led them to believe that the formation would not always be at the optimum moisture content. Furthermore, because the specification for type one sub-base permitted a maximum stone size of 1.5 ins ( and allowing for a laying and a formation dimension tolerance) the depth of sub-base could, in places, be barely more than a stone depth; this too was quite outside the comprehension of a number of highly experienced road builders. As result of these concerns the Ministry's "Concrete Advisory Panel" were consulted. This was a group of three experts who were advising on how to make the concrete roads more competitive and how to resolve difficulties. There is no definitive information available now about their advice but it is apparent that, following their deliberations, no attempt was made to strengthen the sub-base. Within a very short time after opening this section of motorway it was apparent that problems were developing as mud was pumping out of the joint between the pavement concrete and the hard shoulder on the southbound carriageway. Attempts were made to minimize the difficulty by installing a porous drain in the hard shoulder but this was a failure. After a year or so slabs were deflecting significantly and joints were breaking up. Attempts were made to repair joints but on excavation it was apparent that sub-grade softening had occurred. Consequently a number of slabs were replaced. On excavating the formation to provide extra sub-base and waterproofing it was apparent that the surface failure zone in the sub-grade was generally little more than 4 inches thick. Gradually the southbound carriageway joints and slabs failed and eventually the carriageway was reconstructed On the north bound carriageway the experience was somewhat better. The failures of pavement joints and slabs took longer to occur but in time it was also necessary to reconstruct the pavement before it had achieved a reasonable life. The situation which led to the expensive failure of the pavement of Taunton By-pass is an example of how responsibility for decisions can become blurred. The specification was laid down by the Department of Environment centrally. The designers in the Sub-Unit and the Chief Engineer, who were unhappy with the inadequate sub-base, were responsible to the Engineer for the Contract, the Director, he took advice from "Experts". Although it is not known what advice was given it is reasonable to assume that, as the sub-base remained unaltered, they recommended that no changes should be made to the construction depth. Had the responsibility been left with the Sub-Unit the construction depth would have been increased. It is somewhat ironic however that had a greater sub-base depth been included in the Contract it is highly probable that due to the added cost to the concrete alternative, the successful tender would have been for a flexible type of pavement. M5 Chelston to Willand (J26 to J27) The contract for this 11.1 mile length of Motorway was awarded to Tarmac Civil Engineering (now Carrilion Construction) for a tender sum of £12.49m. The scheme commenced at the Chelston Interchange on the Taunton By-pass and ended at the north end of the Cullompton By-pass where the contract included the removal of the slip roads which connected to the A38 road at Willand. Tenders had been invited for alternative forms of pavement construction and Tarmac's (now Carrilion Construction) successful bid was for an 11inch unreinforced concrete slab laid on 11ins of sub-base. The earthworks included 2,400,000 cu.yds of excavation in marles and gravels. There were 42 bridges and culverts and one interchange, at Sampford Peverell, which served as connection to Tiverton and subsequently the North Devon Link Road. An area of alluvial plain in the Lyner Valley where the Motorway is on embankment had to be stabilised by placing a layer of rockfill directly onto the un-removed vegetation. Elsewhere, north of the Sampford Peverill Interchange, the route passed through a wooded area. At the design stage bore holes were taken out on either side of the wood as part of the soils investigation: because of the difficulty in gaining access in the wood and because the two bore holes showed similar soils on either side no samples were obtained in the wood. However when the earthmoving machines traversed the wood it was found to be highly unsuitable and very wet, so that much material was excavated and replaced. This incident is reported as an illustration of the importance in soil survey of understanding the significance of types of vegetation and local names. The wood was called, on the Ordinance Sheet, "Aller Wood"; now in Somerset "Aller" is a corruption of "Alder" and alder trees only grow in boggy ground or near to water. Hence had either of these facts been known to the soil investigators their suspicions would have been aroused and maybe the added costs caused by disruption would have been averted. Tarmac (now Carrilion Construction) used a conventional AGB concreting train operating on rails to pave the full 36 ft. width of each of the carriageways. There were no expansion joints and contraction joints were formed at 20 ft. spacing by vibrating in dowel bars, and sealing strips. On this contract the softened value of the marl sub-grade was assumed to be of a CBR value of 2 . As a result there were no major difficulties with the construction of the carriageway. With the passage of time the riding quality of the carriageway has deteriorated somewhat, particularly due to joint failures, but no major reconstruction has been necessary after 24 years which largely vindicates the concerns expressed by the designers about the inadequacy of the specification on the previous contract. Nineteen bridges were built on this part of the Motorway the largest being crossings of the A38 on heavy skews at Maidendown and near the end of the Cullompton Bypass. An unusual feature in 1974 was the construction of a 24 inch diameter culvert beneath a large embankment to accommodate a well used badger run. In order to make the atmosphere acceptable to badgers a member of the engineering staff crawled through the pipe towing a dead badger skin. M5 Sowton Section (J29 to J30) Work on this 3.8 mile length of motorway was also commenced by the contractors Bovis in May 1973 for a tender sum of £4.95m and was opened with the length to the north in October 1975. The contract extended as far as the interchange on the A3052 serving Exeter, Lyme Regis and Exmouth at Sandy Gate. It also included a spur road from the interchange to the former Exeter Bypass near Countess Weir. A partial interchange with south facing slip roads was constructed at the A30. As it was only a short distance between the A30 interchange and Sandy Gate there was concern about joining and leaving traffic weaving on the motorway carriageway: in order to accommodate these movements a fourth " collector and distributor" lane was included on both carriageways between the two interchanges. The A30 interchange has recently been amended to provide for entry and exit to and from the motorway in a northerly direction. The earthworks required 2,641,000 cu yds of excavation, mainly in Permian sandstone, and the removal of some peat below embankments. 10 bridges were constructed in reinforced concrete and British Rail constructed an under line railway bridge as an advanced contract.
M5 Highbridge By-Pass (J22 to J23) - M5 Bridgwater By-pass (J23 to J24) - Settlement on the Alluvium -
M5 North Petherton By-Pass (J24 to J25) - M5 Taunton By-Pass (J25 to J26) - M5 Chelston to Willand (J26 to J27) -
M5 Killerton Section (J27 to J29) - M5 Sowton Section (J29 to J30) - M5 Exminster Section (J30 to J31)
