M1 in West Yorkshire. Contracts

ON THIS PAGE: This contract was 6.5 miles in length, cost £6 million and commenced in July 1965 and was completed in July 1967. The contractor was Dowsett Engineering Construction Ltd. This contract for the first section of the M1 in the West Riding was started just three months after the start of works at the Leeds end. In the knowledge that contracts for motorways were sometimes subject to 'stop and go' government policies, there was some justification in the thinking of the West Riding engineers that if they started at both ends they were sure to complete the middle. That wasn't quite the case as we shall see. This contract started at, and included part of, the M1/M18 Interchange at Thurcroft, being constructed by Tarmac (now Carrilion Construction) and French, and joined with the lengths of M1 and M18 designed by Sir Owen Williams and Partners. The route enters a cutting, then an embankment down to the crossing of the River Rother, passing through the Catcliffe Interchange, the motorway is carried on embankment to the Tinsley Interchange which links with the two level
Tinsley Viaduct. Heavy earthworks were involved including the removal of steel slag from Firth Brown's tip. This was difficult material, often extrememly hot with clouds of smoke and dust on excavation. A 110RB using both face shovel and dragline bucket was used for excavation and loading into dump trucks. The material was used in the base of the embankments on either side of the River Rother. 14 bridges including 1 railway overbridge, 3 underpasses and 3 subways were constructed, much of the work being sub-contracted. Precast prestressed beams were provided by Dowmac's of Tallington. Darton to Wakefield (J38 to J41) This contract was 6.6 miles in length, cost £7.25 million and commenced in August 1966 and was completed in October 1968. The contractor was Costain Civil Engineering Ltd. The contract involved the construction of two interchanges at Crigglestone and Low Swithen; diversion and improvement of the A637 and the re-alignment and reconstruction of seven existing roads, as well as preparatory work for the Woolley Edge service area. In addition to the 400 ft. long bridge over the River Calder, bridgeworks included 18 overbridges, underbridges and culverts. At Crigglestone work was stopped for over five months to enable the Coal Board to win coal seams that lay under the route of the motorway. The West Riding engineers then allowed for calculated settlement. In one instance a forecast of a 12 in. settlement at a bridge site proved to be correct within an inch. The West Riding engineers were able to prove that the degree of subsidence was predictable under the "Longwall" system of mining used. On this section of motorway advantage was taken of sidelong ground to separate line and level carriageways in the interest of economy of earthworks and also to increase the visual interest of the motorist, often an important consideration in safer driving. Plant used by the contractors for the earthworks included rubber-tyred 657's and TS24 motor scrapers; some DW12's and a few crawler hauled units. Soil was compacted by the self propelled DW21/Hyster grid roller which travelled at 10-12 m.p.h. and 72 T's. The formation level was finished by motor graders prior to being sealed by surface dressing with tar and chippings. The surfacing sub-contractor Ameys Asphalt used an 18 ft. Vogele paver for laying the base and PF90's for the wearing course. Asphalt production plants were established locally. The collapse of the Calder Bridge cast a shadow over the contract and is dealt with elsewhere. Wakefield to East Ardsley(J41 to J42) This contract was 4.6 miles in length, cost £4 million and commenced in August 1965 and was completed in April 1967. The contractor was the Sir Alfred McAlpine, Leonard Fairclough Consortium. The contract extended from south of the A650 Ardsley Interchange on embankment into cutting at Kirkhamgate, over deep embankment adjacent to Wrenthorpe Golf Course rising to the A638 Dewsbury Road Interchange, then crossing Queen Drive and terminating at the Horbury Road Bridge. Interesting VariationOrders included the erection of the motorway fencing, the provision of a boat to take soundings in the old gravel workings and the strengthening of the floor of an archway under the railway which provided the lorry access to the flooded gravel workings. The work was completed before the start of the adjacent contract. The rock came by road from a quarry in Morley. The contract was extended because the earthworks' balance went seriously wrong when the predicted unsuitable material in the Snapethorpe cutting turned out to be suitable. The Use of Colliery Shale. Shale from the tip east of the M1 and south of Queens Drive was used in the works. When excavated it was hot and caused clouds of dust to drift across the site towards Ossett. Queens Drive Bridge. An existing concrete retaining wall 3 - 4m high supporting the south-side of Queens Drive, one day slowly rotated and collapsed in text-book fashion because the support at the front of the wall had been removed. Dewsbury Road Interchange Bridges. Some of the spans were jacked up and down 2 or 3 times because the pre-cast concrete bearings kept on cracking. The idea for the bearings came from a table at the back of a Reinforced Concrete Designers handbook, and our design failed to take into account of the inaccuracies in the manufacture of the pre-cast units, and resulted in the point loading of the bearings. Eventually layers of lead were used to spread the loading over the appropriate area of the bearings. Wakefield - Ossett Railway Line. The original contract included the provision of a single span underbridge to carry the M1 over the railway, but early in the contract period, British Rail indicated that they were going to close the line. The Resident Engineer got a "rocket" from Fred Oliver for phoning British Rail at York and trying to speed up the decision. The bridge was deleted from the contract and an embankment for the motorway was constructed in the railway cutting. This cutting also provided endless source of sample carpet squares, which had been tipped, for the homes of the site staff. Bushy Beck. The National Coal Board removed all the coal from under the motorway embankment before the contract started. The replacement of material up to original ground level was supervised by county engineers. A multi-plate armco culvert carried the stream under the M1 and in the early days of the contract one of our engineers Andy Peach wrote off a Land Rover by driving it into the excavation for the culvert. He was not seriously hurt. One morning, after a period of continuous rain, when the embankment, carriageway drainage and pavement were complete, water was found to be pouring out of the side of the embankment 1 - 2m below carriageway level. To cut a long story short, a number of gully connections had not been correctly made. This event led to the use of CCTV cameras to check the construction of the drainage on other sections of the M1. Old Mine Workings, South of Batley Road. Again, after a period of rain, the eastern side of the cutting immediately south of Batley Road collapsed. It was riddled with horizontal addits. The side of the cutting was excavated and reformed. Grout was injected into the old workings under the underpass from the Batley Road to Gawthorpe. All the coal from the shallow workings under the bridge and the surrounding area was removed to an NCB depot. The collapsed old workings and the supporting pillars of coal could be clearly seen in the temporary diversion of the road. Entry into the Supervisor of Works' office on the Batley Road, was sometimes impossible. It was full of plastic sacks full of coal. Underpass South of Bradford Road. As soon as the motorway was complete, the ends of this accommodation underpass were blocked up and it was used to force rhubarb. Hard-shoulder Treatment. The contract included the use of a very expensive white Norwegian stone (calcine flint) on the hard shoulder and after a trial length on the south bound carriageway north of the Batley Road, and discussions between Hutch and the County Engineer, the specification was changed to a less expensive treatment. Conclusion The M1 Motorway by now was completed to the outskirts of Leeds at Stourton. The completion of the motorway to the city centre came later and is covered under 'The City motorways'. A. Monk & Co. of Warrington commenced the first section from East Ardsley terminating at the Leeds City Boundary in May 1965 and were followed in August by the Sir Alfred McAlpine and Leonard Fairclough Consortium on the adjacent section to the south. By December 1965, the latter firm in 3 months had excavated and compacted in embankment upwards of 1million cu. yds. of earthworks and within 18 months had satisfactorily completed their works. In the meantime A. Monk & Co. made good progress in spite of suspension to the north at Sharpe Lane where coal extraction was taking place in the Robin Hood area. By August 1967 a section of the motorway was opened between the Dewsbury Road and Bradford Road interchanges and in October work to the Leeds City Boundary was completed both assisting local traffic. The southernmost section from Aston to Tinsley Viaduct was let to Dowsett Engineering Construction Ltd. who within two years had completed their works and with the later completion of the M1 and M18 contracts to the south (in December 1967) connected Sheffield to London and the A1(M) Doncaster By-pass. During this period the Tinsley Viaduct between Sheffield and Rotherham was under construction and to the north a further four major contracts were let in rapid succession to Holland & Hannen & Cubitts, A. Monk & Co. Ltd. (2nd contract), Dowsett Engineering Construction Co. Ltd. (2nd contract) and Costain Civil Engineering. By June 1968 works were completed to the Tankersley interchange south of Barnsley and with the completion of Tinsley Viaduct enabled traffic to advance up the M1 from London to Barnsley. By August the motorway became viable to Dodworth, leaving the remaining 10 miles for completion in October within the contract period. The last section of the M1 in the West Riding was completed in October 1968 following which it was formally opened by the Rt. Hon. Richard Marsh MP, who drove the full length from Aston to Leeds. Sir Owen Williams and Partners had completed their section of M1 through Nottinghamshire and had progressed the M18 from M1 to the Doncaster By-pass A1(M). It was inevitable that during the 3½ year period during which 35 miles of motorway and 40 miles of side roads associated with the motorway were under construction that some inconvenience to local life would occur. Not withstanding this, genuine interest was shown by all members of the community in this vast undertaking. To achieve completion some 13 million cu. yds. of excavation in all materials have been placed as fill in embankments and a further 2 million cu. yds. of fill have been imported from local sources including some 200,000 tons of pulverised fuel ash from Thorpe Marsh Power Station. During operations approximately 50,000 tons of surface coal was exposed and removed, of which 21,000 tons of useable coal was delivered to the NCB. Approximately 250 miles of drains of all types have been laid and 2¾ million sq. yds. of road pavement constructed on both the motorway and associated side roads. The final costs for the whole of the M1 motorway in West Yorkshire was in the order of £36.8 million excluding Tinsley Viaduct and the River Calder Bridge. Perhaps the most impressive statistic being for settlement claims by contractors which amounted to only 2.1% of total expenditure.
Aston to Tinsley (J31 to J34) - Meadowhall to Blackburn (J34 to J35) - Blackburn to Tankersley (J35 to J36) -
Tankersley to Darton (J36 to J38) - Darton to Wakefield (J38 to J41) - Wakefield to East Ardsley (J41 to J42) -
East Ardsley to Stourton (J42 to J44) - Conclusion

