Region: North East
M18. Doncaster By-pass (Wadworth) to M62 (J2 to J7)
INDEX TO SECTIONS The construction of the M18 motorway provided a motorway link between the M1 near Rotherham and the M62 near Goole and closed the motorway box around the towns of Pontefract , Wakefield, Barnsley, Rotherham and Doncaster. The motorway is also linked to the A1(M) at Doncaster and the M180 south of Thorne. The M18 from Rotherham to the A1(M) Doncaster By-pass has already been described . This account covers the motorway to the east of A1(M) to Goole. This length of the M18 from Thorne back to the Doncaster By-pass was divided into the following contracts: The contracts were carried out over a period of six years from 1970 to 1978 by the North Eastern Road Construction Unit and the West Riding and West Yorkshire Sub-Units. Hatfield to Thorne (Thorne By-pass) (J5 to J6) This contract was awarded to Sir Alfred McAlpine & Sons in the tender sum of £4.798 million and work started on the 1st September 1970. This 3.6 mile section of M18 which was opened to traffic in June 1972 runs from a point on the Hatfield - Thorne Road A1146 to join the A614 at Waterside to the N W of Thorne. The Tudworth link is approximately one mile in length stretching east from the two level motorway interchange at North Ings to a point near Tudworth Hall Corner. Approximately 2 million cu. yds. of fill material were imported and included unburnt colliery shale from Hatfield tip near Thorne and bunter sandstone. Of the 14 structures on the contract the major one is the East Ings Canal Bridge which carries the motorway over the Stainforth - Keadby Canal. The bridge has three spans , an overall length of 242 ft. with two piers founded on piles and the bank seats on embankment filling. Approximately 175,000 cu. yds. of peat (with bog oak) located on each side of the canal had to be excavated up to a depth of 20 ft. prior to commencing filling. 54RB Draglines were used standing on timber mats to spread the load. Material was passed from machine to machine until firm ground was reached. The work involved the prior protection of the canal banks with sheet piling, in order to avoid the possibility of draining several miles of canal. Unfortunately the piling did not toe into the underlying Bunter Sandstone, and so led to the removal of all the peat from under the south bridge abutment and to the need to jack up the bridge deck later in the contract. Strain gauges were installed on the H-piles to establish loading conditions, and laboratory tests carried out to determine the Young's modulus for the imported Bunter Sandstone, colliery shale and fly ash and predict settlement. The motorway construction programme has resulted in a large increase in the number of medium span bridges. Indeed, the 500th bridge to be built in the West Riding of Yorkshire since the beginning of the motorway programme is now in the planning stage. The design of the substructures associated with these bridges is usually based on lateral earth pressures calculated using the classical earth pressure theory originally proposed by Coulomb in 1776, and many of them take the form of abutments having cantilever wing walls. In 1966 the West Riding County Council acting with the then Ministry of Transport initiated some tests into the earth pressures acting on the retaining walls. The earth pressures acting on the four abutments of the North Ings Interchange bridges on the M18 motorway have been measured, together with the earth pressure acting on a cantilevered wing wall. Different backfilling materials have been studied. The results of the investigation compare favourably with the results of a three-dimensional finite element analysis which is considered to represent a more valid design approach." Wadworth Viaduct The contract covered road and bridgeworks which extended the existing Northern to Wadworth section of the M18 across the A1(M) Doncaster By-pass to link with the Wadworth to Armthorpe section of the M18. Wadworth Viaduct carries the M18 over the A1(M) interchange roundabout, White Cross Lane and the A1(M). The viaduct has seven 39.25 metre spans and there is a longitudinal joint between the carriageways. The deck for each carriageway is constructed of 6 longitudinal steel plate girders acting compositely with a reinforced concrete deck slab. The longitudinal connections between the plate girders were originally designed as plated, with friction grip bolts. However, an alternative proposal by the steel-work subcontractors for site welded connections was accepted. The girders were fabricated in approximately 20m sections and welded on site to form a continuous construction. Generally two beam sections were welded together on the ground to give a lifting length of 39.25m., which were lifted into place in pairs for stability during erection. Air welds were made at the quarter points of each span (with the exception of the first span) so that the lifted in length comprised of ¾ of one span plus ¼ of the next. For the first span the beams were lifted in 50m lengths to form the first span plus ¼ of the next. To keep within the load carrying capacity of the cranes on site, these beams were lifted in singly, with stability provided by temporary bow strings to the top flanges. Each deck is supported by reinforced concrete abutments and six pairs of reinforced concrete piers, each pier is tapered and widens out at the top to form a crosshead. All piers and abutments are supported on steel H-piles, with an average length of 12m, driven down into the Middle Permian Marl, except for the south abutment where the piles were driven on to a limestone layer. Steel H-piles were selected because of the aggressive ground conditions, with sulphate concentrations up to class 5. This rendered the use of concrete piles impracticable, and necessitated the waterproofing of the pier and abutment bases, in addition to the use of sulphate resisting cement. Roadworks entailed the construction of approximately 250 metres of motorway connecting the completed section of the M18 from the west with the viaduct together with its surfacing. The motorway has an overall width of 17.6 metres consisting of dual carriageways each 7.3 metres wide incorporating 0.7 metres wide hard strips. There are two outside margins each 4.8 metres wide consisting of a 3.3 metre wide hardshoulder including a marginal strip and a 1.5 metre verge. The carriageways were constructed of approved flexible materials comprising sub-base, road base and a flexible surfacing of two courses having a minimum final thickness of 100mm which extended over the viaduct.
Introduction - Thorne to East Cowick (J6 to J7) - Hatfield to Thorne (Thorne By-pass) (J5 to J6) -
Armthorpe to Hatfield (J4 to J5) - Wadworth to Armthorpe (J2 to J4) - Wadworth Viaduct

